Underpass bridge work in Grand Forks to continue through winter

The North Dakota Department of Transportation says bridge work on the Grand Forks underpass project will continue through winter as weather allows.

By Grandforks Local Staff
Ask AI

Summarize this page with

ChatGPTClaudePerplexityGoogle AI
Editorial illustration: Underpass bridge work in Grand Forks to continue through winter

In short

  • The North Dakota Department of Transportation says bridge work on the 42nd Street and DeMers Avenue Underpass project in Grand Forks will continue ...
  • The department said crews this year built a temporary DeMers Avenue bypass and shared-use path, installed a water main beneath the BNSF Railway tra...
  • This winter, crews are scheduled to work on bridge foundations and supports, NDDOT said.

The North Dakota Department of Transportation says bridge work on the 42nd Street and DeMers Avenue Underpass project in Grand Forks will continue through winter as weather allows, with full construction scheduled to resume in spring 2027.

The department said crews this year built a temporary DeMers Avenue bypass and shared-use path, installed a water main beneath the BNSF Railway tracks, built a temporary rail line and completed excavation for both bridges. This winter, crews are scheduled to work on bridge foundations and supports, NDDOT said.

Traffic patterns are not expected to change over winter, according to the department. The DeMers Avenue and 42nd Street intersection remains closed, and DeMers Avenue traffic will continue using the temporary bypass connecting to South 42nd Street. NDDOT said 42nd Street remains closed north of the bypass to James Ray Drive.

Detours remain in place, the department said. Passenger vehicles can use Gateway Drive/U.S. Highway 2, 17th Avenue South and Columbia Road; semitrucks can reach the area via Washington Street using the 32nd Avenue South or Gateway Drive interchanges.

The shared-use path along the bypass provides east-west pedestrian access on DeMers Avenue and will be cleared of snow through winter, NDDOT said. The department said north-south pedestrian access is unavailable at the intersection, with Columbia Road the nearest north-south route.

NDDOT said DeMers Avenue traffic is scheduled to shift onto the new bridges in summer 2027, and 42nd Street is scheduled to reopen in fall 2027. Major construction is expected to be complete in fall 2027, with final work wrapping up in spring 2028, according to the department. Project updates are available at dot.nd.gov/42ndDemersUnderpass, and road conditions and construction information are available by calling 511 or visiting the ND Roads map at travel.dot.nd.gov, NDDOT said.